MS Project makes calculation based on the following formula:
DURATION = WORK / ASSIGNMENT UNITS
So, if a resource can complete a task by working for 8hrs. full time, i.e. 100% on a task its duration is 8 hrs. If the resource works only half day, i.e . 50%, the task duration becomes 16 hrs.
DURATION |
WORK |
ASSIGNMENT UNITS |
8 hrs. |
8 hrs. |
1 (100%) |
16 hrs. |
8 hrs. |
0.5 (50%) |
We can fix any one parameter for the project while scheduling:
When one parameter is fixed and we enter or change another, the third gets calculated automatically.