You are here

Type of Construction Drawings

 

Type of Construction Drawings

1 -  Preliminary Drawings .  (design concepts)      

2 - Contract drawings.

3 - Working drawings . (actual construction)    

4 - Shop drawing. (between design and construction)

5 - As-built drawings. (as completed or executed)

1 -  Preliminary Drawings

  • Preliminary drawings prepared to the degree that owner can visualize the total project.
  • Preliminary drawings complete enough to allow the preparation of a realistic budget estimate.
  • Anything that can contribute to a more complete understanding of the client shall be considered.

2  Contract drawings.

  • The contract drawings are used as an essential part of the contract.
  • Keep a set on the job with all changes and revisions posted.

3  Working drawings .

  • Based on the design presented in the preliminary drawings, approved by owner.
  • The Working Drawings include all the information needed to obtain a building permits
  • The approved design is not changed but it is further developed, defined, and improved.
  • Working drawings together with specifications give complete picture of the project.
  • Used by several groups of people.  Hence should be prepared to meet the requirement of each group.
  • Contain detail dimensioning information that establishes:

             Sizes, Relationships, and Location of all elements of the project.

 

4  Shop drawing.

A shop drawing is a drawing or set of drawings produced by the contractor, supplier, manufacturer, subcontractor, or fabricator.

  • Shop drawings are reviewed by the design professional.
  • Approval of the shop drawings by Design Professional is a restricted approval (check against the intent of design drawings only)
  • Shop drawings are actually an extension and further development of working drawings.
  • Shop drawings do not change the intent of the working drawings.
  • Prepared by subcontractors or material suppliers.  In some cases also by the general contractor.
  • Shop drawings are provided for works such as:  Installation and fabrication, structural steel, mill work, metal windows and doors, pipes and pumps and etc.....
  • Responsibility of errors and omissions in shop drawings lies with the contractor/subcontractor.
  • Timely approval of shop drawings is of prime importance!
  • Shop drawings approval may effect project schedule, if not submitted on time.
  • Record shop drawings in contractor’s submittal log.
  • Shop drawings should be stamped and dated immediately upon receipt.

 

5  As-built drawings

  • Most specifications require that the contractor refrain from ordering material until the shop drawings are approved officially.  (IN WRITING)
  • Usually these are “location drawings” to which the owner may refer for maintenance and repairs.
  • Working drawings show ”proposed” locations for pipes, valves, man holes, etc....., as built drawings show “actual” locations, of installations.
  • Usually general contractor or sub-contractors prepare as-built drawings.
  • Requirement for as-builtdrawing, should be included in bidding documents.
  • If not included in the contract documents, and if required legally, can be added by issuing a change order.
  • The term as-built drawings in unpopular because of some legal difficulties with some design professionals. 

 

Legal  Requirements :

  • Seal of design professional.
  • Seal of surveyors for site drawings.
  • Seal of AE for general project drawings.
  • Seal on various supporting drawings by related design professional e.g..  Landscape architect, mechanical/electrical engineer.

Each drawing sheet must contain a title block with:

  • Number of project and sheet
  • Date of drawings
  • Type of information (plan, section)
  • Name of design professional
  • Checked by, date checked, etc.....

 

Source :

Arizona State University


 

 

 

Forums: