MSP 4.2 Setting Up Equipment Resources

 

Setting Up Equipment Resources

This includes:

1-What are Equipment Resources

2-How to enter Equipment Resource Names

Equipment Resources are work based resources like people resources. E.g. for a task like excavation - excavator, backhoe etc. are the equipments. They are usually rented on per hour/ day / week basis. These can also have a cost per use. These are not added as Material resources because these are not consumed in the project process

 

 